CALCULATION OF HUMAN RESOURCES USING THE RESOURCE LEVELING FOR LABOR EFFICIENCY IN THE NEW MARKET DEVELOPMENT PROJECT OF MANDAILING NATAL REGENCY

  • Nessi Deva Fitriani Politeknik Negeri Medan
  • Mizanuddin Sitompul Politeknik Negeri Medan
Keywords: resource leveling, alokasi tenaga kerja, microsoft project

Abstract

Manpower is one of the important human resources often limited availability, either
due to quality factors or other reasons. In the construction phase, there is often a
problem of unequal labor requirements that affect the allocation of labor. To minimize
labor fluctuations using the resource leveling method. This study aims to determine
the effect of resource leveling on the workforce on the allocation of labor on the construction under review and determine the allocation of human resources in
implementation based on planning data. The object of this research is the construction
of a new market in the Mandailing Natal district. The technique used in the resource
leveling method research uses the help of the microsoft project program. This study
shows that there is an influence of resources leveling on the workforce (workers,
builders, head builders, foreman) on the allocation of labor in construction. The
available workface are 50 workers, 32 carpenters, 22 carpenters, 2 head craftsmen, 1
foreman with a duration of work of 330 days. The leveling results show that with the
available workforce, both with a fixed or unrestricted duration of work, there are some
workers who are overallocated. From the results of the analysis, for a work duration
of 330 days, the required number of workers includes 91 workers, 41 carpenters, 16
carpenters, 3 head craftsmen, 3 foreman.

References

Daeli Nur Indahty, 2020. Perhitungan Sumber Daya Manusia Dengan Metode Resouce Leveling Menggunakan Bantuan Microsoft Project Pada Proyek Pembangunan Gedung Olahraga Kecamatan Bunguran Timur. Skripsi. Teknik Sipil Politeknik Negeri Medan : Medan.

Edwin B. Flippo., T. Tani Handoko, 1998. Manajemen Personalia dan Sumber Daya Manusia. Yogyakarta: BPFEE

Gray, C.F., Larson, E.W. 2007. Manajemen Proyek Proses Manajerial. Yogyakarta: Andi

Harley., Bowin, 1996. Human Resources Management: An Experience Approch. Prentice Hall

Husen, A. 2011. Manajemen Proyek Perencanaan Penjadwalan dan Pengendalian Proyek. Yogyakarta: Andi

Putra Kelana, Rama, 2010. Optimalisasi Penggunaan Sumber Daya Manusia Dengan Metode Resources Levelling Menggunakan Bantuan Microsoft Project 2007. Skripsi. FT. Teknik Sipil. Universitas Sebelas Maret : Surakarta.

Putra, R., Sugiono, S., Sari, R A, 2015. Perencanaan Penjadwalan Multi Proyek Konstruksi Dengan Keterbatasan Sumber Daya Manusia Menggunakan Resource Leveling Method. Jurnal Rekayasa, Vol. 3, No.3, p. 463-474.

Retno, Deddy Purnomo., Astuti, Astuti., Tamimi, Zulfadli, 2018. Analisa Penggunaan Sumber Daya Manusia Dengan Metode Resource Leveling Pada Pelaksanaan Proyek Konstruksi (Studi Kasus : Proyek Pembangunan Ruang Kelas Baru Ponpes Daarun Nahdah Thawalib Bangkinang). Jurnal Saintis, Vol. 18, No.1, p. 39-47.

Soeharto, Imam, 1997 Manajemen Proyek dari Konseptual Sampai Operasional. Jakarta: Erlangga.

Yani, Victor., Chandra, Albert, 2015. Penerapan Resource Allocation Dan Leveling Tenaga Kerja Dengan Menggunakan Microsoft Project 2010 Pada Suatu Proyek Konstruksi, p. 1-8.

Published
2021-10-28
How to Cite
Nessi Deva Fitriani, & Sitompul, M. (2021). CALCULATION OF HUMAN RESOURCES USING THE RESOURCE LEVELING FOR LABOR EFFICIENCY IN THE NEW MARKET DEVELOPMENT PROJECT OF MANDAILING NATAL REGENCY. Jurnal Media Teknik Sipil Samudra, 2(2), 1-10. Retrieved from https://ejurnalunsam.id/index.php/jmtss/article/view/3994
Section
Articles